# AI Buildout Tracker

Hyperscaler capex, tracked data center mega-projects, and power deals. Every row is individually sourced and linked to the exposed tickers. Firm power contracts are counted apart from non-binding letters of intent.

## Totals

| Measure | Value |
| --- | --- |
| Trailing-twelve-month capex (tracked companies) | $751.4B across 7 companies |
| Tracked projects | 121 projects, 114.1 GW |
| Under construction or operating | 69.7 GW across 80 projects |
| Announced only | 44.5 GW |
| Firm power deals | 50.5 GW across 47 deals |
| Letters of intent | 20.9 GW across 8 deals |

## Hyperscaler capex

| Company | Latest quarter | Quarter capex ($B) | TTM capex ($B) | YoY | Guidance | Source |
| --- | --- | --- | --- | --- | --- | --- |
| Amazon ([AMZN](https://supercyclehq.com/stock/amazon.md)) | Q3 2026 | 75.9 | 214.1 | +122.0% | Reaffirmed full year 2026 cash capex guidance of about $220B and said it expects to spend meaningfully more in 2027. | [2026-10-29](https://www.cnbc.com/2026/10/29/amazon-amzn-q3-earnings-report-2026.html) |
| Alphabet ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Q3 2026 | 51.4 | 159.8 | +115.0% | Reaffirmed full year 2026 capex guidance of $195B to $205B and said capex will increase significantly again in 2027. | [2026-10-28](https://fourweekmba.com/ai-google-cloud-revenue-doubles-to-30-7b-as-capex-hits-51-4b/) |
| Microsoft ([MSFT](https://supercyclehq.com/stock/microsoft.md)) | FY27 Q1 | 45.2 | 155.6 | +30.0% | Guided fiscal Q2 2027 capex including finance leases to exceed $50B, said full fiscal 2027 capex will grow year over year on demand signals, and reaffirmed calendar 2026 capex of about $175B outside the useful life accounting change. | [2026-10-28](https://www.cnbc.com/2026/10/28/microsoft-msft-q1-earnings-report-2027.html) |
| Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Q3 2026 | 34.9 | 107.9 | +80.0% | Narrowed full year 2026 capex including finance lease principal payments to $135B to $145B, raising the floor from $130B. | [2026-10-21](https://s21.q4cdn.com/399680738/files/doc_news/Meta-Reports-Third-Quarter-2026-Results-2026.pdf) |
| Oracle ([ORCL](https://supercyclehq.com/stock/oracle.md)) | FY27 Q1 | 28.5 | 75.7 | +235.0% | Reiterated fiscal 2027 guidance of up to about $95B of gross capex, with net cash capex not to exceed $70B after customer prepayments. | [2026-09-10](https://www.cnbc.com/2026/09/10/oracle-orcl-q1-earnings-report-2027.html) |
| CoreWeave ([CRWV](https://supercyclehq.com/stock/coreweave.md)) | Q2 2026 | 9.4 | 27.2 | +224.0% | Raised full year 2026 capex guidance to $35B to $39B, with Q3 2026 capex expected between $11.5B and $13.5B. | [2026-08-11](https://s205.q4cdn.com/133937190/files/doc_financials/2026/q2/CRWV-US-CORRECTED-TRANSCRIPT-CoreWeave-Q2-2026-Earnings-Call-11August2026.pdf) |
| Nebius Group ([NBIS](https://supercyclehq.com/stock/nebius-group.md)) | Q2 2026 | 5.7 | 11.1 | +1008.0% | Reaffirmed 2026 capex guidance of $20B to $25B alongside a raised year-end contracted power target of 5 GW. | [2026-08-12](https://assets.nebius.com/assets/a6ecfd85-a6cb-4967-8ef7-9a25bd261f9c/SHLQ226.pdf) |

## Data center projects

| Project | Operator | Location | Capacity (MW) | Status | Target | Investment ($B) | Exposed tickers | Source |
| --- | --- | --- | --- | --- | --- | --- | --- | --- |
| Project Matador | Fermi America ([FRMI](https://supercyclehq.com/stock/fermi-inc.md)) | Amarillo, TX | 11000 | Under construction | n/a | n/a | [FRMI](https://supercyclehq.com/stock/fermi-inc.md) operator; [GEV](https://supercyclehq.com/stock/ge-vernova.md) power | [2026-10-09](https://www.federalregister.gov/documents/2026/10/09/2026-20742/fermi-america-llc-dba-fermi-america-project-matador-advanced-energy-and-intelligence-campus-ap1000) |
| Project Beehive | Valar Atomics | Price, UT | 9600 | Announced | 2032 | n/a | n/a | [2026-09-30](https://www.npr.org/2026/09/30/nx-s1-5983482/valar-atomic-nuclear-data-center-project-beehive-utah) |
| PORTS-Pike Technology Campus | SB Energy | Pike County, OH | 8000 | Announced | 2028 | 105 | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips; [AEP](https://supercyclehq.com/stock/american-electric-power.md) power | [2026-08-17](https://nvidianews.nvidia.com/news/nvidia-guarantees-sb-energy-s-ports-pike-technology-campus-in-ohio-to-exclusively-host-nvidia-ai-compute) |
| Meta Hyperion | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Richland Parish, LA | 5000 | Under construction | 2030 | 50 | [META](https://supercyclehq.com/stock/meta-platforms.md) operator; OWL investor; [ETR](https://supercyclehq.com/stock/entergy.md) power | [2026-07-13](https://www.cnbc.com/2026/07/13/meta-louisiana-data-center-investment-reaches-50-billion-amid-ai-push.html) |
| OpenAI Project Camellia (Effingham County) | OpenAI | Effingham County, GA | 3200 | Announced | 2032 | 20 | [SO](https://supercyclehq.com/stock/southern-company.md) power | [2026-07-22](https://www.datacenterdynamics.com/en/news/openai-reveals-32gw-data-center-project-in-effingham-county-georgia/) |
| Matrix Data Center Campus | MSB Global Services | Sulphur Springs, TX | 3000 | Under construction | 2029 | 18.7 | [BE](https://supercyclehq.com/stock/bloom-energy.md) power | [2025-06-13](https://msbglobalservices.com/matrix-data-center-campus-breaks-ground-in-sulphur-springs-tx-a-new-era-for-net-zero-ai-infrastructure/) |
| Project Tembo | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Cheyenne, WY | 2700 | Under construction | 2031 | n/a | [GOOGL](https://supercyclehq.com/stock/alphabet.md) operator; [BKH](https://supercyclehq.com/stock/black-hills.md) power | [2026-10-06](https://www.sec.gov/Archives/edgar/data/0001130464/000119312526415597/bkh-ex99_1.htm) |
| Stargate Project Jupiter | STACK Infrastructure | Doña Ana County, NM | 2200 | Under construction | 2028-12 | 165 | [ORCL](https://supercyclehq.com/stock/oracle.md) tenant | [2026-09-17](https://sourcenm.com/2026/09/17/new-mexico-supreme-court-rejects-2-project-jupiter-challenges-allows-permitting-process-to-resume/) |
| Project Rainier | Amazon Web Services ([AMZN](https://supercyclehq.com/stock/amazon.md)) | New Carlisle, IN | 2200 | Partially operational | n/a | 11 | [AMZN](https://supercyclehq.com/stock/amazon.md) operator; [AEP](https://supercyclehq.com/stock/american-electric-power.md) power | [2025-10-29](https://www.aboutamazon.com/news/aws/aws-project-rainier-ai-trainium-chips-compute-cluster) |
| Stargate Abilene (Crusoe AI Factory) | Crusoe | Abilene, TX | 2100 | Partially operational | 2027 | 15 | [ORCL](https://supercyclehq.com/stock/oracle.md) tenant; [MSFT](https://supercyclehq.com/stock/microsoft.md) tenant; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips; OWL investor | [2026-03-27](https://crusoe.ai/resources/newsroom/crusoe-announces-new-900-mw-ai-factory-campus-in-abilene-texas-to-support-microsoft-ai-infrastructure) |
| Sweetwater Campus | IREN ([IREN](https://supercyclehq.com/stock/iris-energy.md)) | Sweetwater, TX | 2000 | Partially operational | n/a | n/a | [IREN](https://supercyclehq.com/stock/iris-energy.md) operator; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-05-06](https://www.datacenterdynamics.com/en/news/iren-energizes-first-phase-of-2gw-sweetwater-data-center-campus-in-texas/) |
| Project Phoenix | Aligned Data Centers | Shippingport, Beaver County, PA | 2000 | Under construction | n/a | 10 | n/a | [2026-09-10](https://www.datacenterdynamics.com/en/news/aligned-breaks-ground-on-gigawatt-scale-data-center-campus-in-pennsylvania/) |
| Muskogee Campus | Core Scientific ([CORZ](https://supercyclehq.com/stock/core-scientific.md)) | Muskogee, OK | 1500 | Under construction | 2027 | n/a | [CORZ](https://supercyclehq.com/stock/core-scientific.md) operator; [OGE](https://supercyclehq.com/stock/oge-energy.md) power | [2026-08-14](https://investors.corescientific.com/news-events/press-releases/detail/142/core-scientific-completes-acquisition-of-polaris-ds-advancing-planned-muskogee-expansion-to-1-5-gw-of-gross-power) |
| Pecos Campus | Core Scientific ([CORZ](https://supercyclehq.com/stock/core-scientific.md)) | Pecos, TX | 1500 | Under construction | 2027 | n/a | [CORZ](https://supercyclehq.com/stock/core-scientific.md) operator | [2026-04-27](https://investors.corescientific.com/news-events/press-releases/detail/134/core-scientific-plans-expansion-to-1-5-gigawatts-of-gross-power-at-pecos-texas-campus) |
| Homer City Energy Campus | Homer City Redevelopment | Homer City, PA | 1500 | Under construction | 2027 | 10 | [GEV](https://supercyclehq.com/stock/ge-vernova.md) equipment | [2026-06-23](https://constructionreviewonline.com/news/former-homer-city-plant-to-become-a-10-billion-ai-data-center-campus/) |
| Western Downs Digital Park | Zerra DC (Dexus and Macquarie) | Dalby, Queensland, Australia | 1440 | Announced | 2027 | 32 | n/a | [2026-09-18](https://www.abc.net.au/news/2026-09-18/queensland-data-centre-ai-anthropic-explainer/107163376) |
| Frontier | Vantage Data Centers | Shackelford County, TX | 1400 | Under construction | 2028-12 | 25 | [ORCL](https://supercyclehq.com/stock/oracle.md) tenant; [DBRG](https://supercyclehq.com/stock/digitalbridge-group.md) operator | [2025-08-19](https://www.businesswire.com/news/home/20250819291091/en/Vantage-Data-Centers-Unveils-Plans-for-Frontier-a-25B-Mega-campus-in-Texas-to-Meet-Unprecedented-AI-Demand) |
| Stargate The Barn (Saline Township) | Related Digital | Saline Township, MI | 1400 | Under construction | 2028-12 | n/a | [ORCL](https://supercyclehq.com/stock/oracle.md) tenant; [DTE](https://supercyclehq.com/stock/dte-energy.md) power | [2026-04-17](https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand) |
| Texas Critical Data Centers (TCDC) | New Era Energy & Digital (NUAI) | Odessa, TX | 1400 | Announced | 2027-09 | n/a | [VST](https://supercyclehq.com/stock/vistra-energy.md) power | [2026-09-21](https://www.sec.gov/Archives/edgar/data/0002028336/000121390026101642/ea0305716-8k_newera.htm) |
| MGX-Mistral AI Paris Campus (Essonne) | MGX / Mistral AI consortium | Essonne (near Paris), France | 1400 | Announced | 2028 | n/a | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2025-05-20](https://www.datacenterdynamics.com/en/news/mgx-bpifrance-nvidia-and-mistral-ai-plan-14gw-paris-data-center-campus/) |
| Monarch Compute Campus | Nscale | Mason County, WV | 1350 | Under construction | 2028 | 20 | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-08-27](https://www.datacenterdynamics.com/en/news/anthropic-signs-45bn-compute-capacity-agreement-with-nscale-report/) |
| Stargate Lighthouse (Port Washington) | Vantage Data Centers | Port Washington, WI | 1300 | Under construction | 2028-12 | n/a | [ORCL](https://supercyclehq.com/stock/oracle.md) tenant | [2026-04-17](https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand) |
| Stargate Milam County | SB Energy / SoftBank | Milam County, TX | 1200 | Under construction | 2028-12 | n/a | n/a | [2026-04-17](https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand) |
| Google New Florence Data Center | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | New Florence, MO | 1200 | Announced | n/a | 15 | [GOOGL](https://supercyclehq.com/stock/alphabet.md) operator | [2026-05-20](https://www.datacenterdynamics.com/en/news/google-pledges-15bn-investment-in-new-florence-missouri/) |
| Nebius Independence AI Factory | Nebius ([NBIS](https://supercyclehq.com/stock/nebius-group.md)) | Independence, MO | 1200 | Under construction | n/a | n/a | [NBIS](https://supercyclehq.com/stock/nebius-group.md) operator | [2026-05-12](https://www.datacenterdynamics.com/en/news/nebius-breaks-ground-on-400-acre-data-center-campus-in-independence-missouri/) |
| Nebius Highridge Business Park AI Factory | Nebius ([NBIS](https://supercyclehq.com/stock/nebius-group.md)) | Butler Township, Schuylkill County, PA | 1200 | Announced | 2027-10 | n/a | [NBIS](https://supercyclehq.com/stock/nebius-group.md) operator | [2026-07-31](https://www.datacenterdynamics.com/en/news/nebius-details-plans-for-12gw-data-center-campus-in-pennsylvania/) |
| Paducah AI Campus | Brookfield (BAM) | Paducah, KY | 1200 | Announced | 2032 | 100 | BAM investor; [NEE](https://supercyclehq.com/stock/nextera-energy.md) power | [2026-07-29](https://www.powermag.com/brookfield-nextera-to-develop-100b-data-center-campus-at-does-paducah-site-paired-with-4-6-gw-of-dedicated-generation/) |
| Bell AI Fabric Saskatchewan (Sherwood Headquarters) | Bell Canada ([BCE](https://supercyclehq.com/stock/bce.md)) | Rural Municipality of Sherwood, near Regina, Saskatchewan, Canada | 1200 | Under construction | 2027 | n/a | n/a | [2026-09-14](https://www.cbc.ca/news/canada/saskatoon/bell-canada-ai-data-centre-size-expansion-investment-9.7343780) |
| Goodnight Campus (Project Llano) | Crusoe | Armstrong County, TX | 1030 | Under construction | 2027-02 | 29 | [GOOGL](https://supercyclehq.com/stock/alphabet.md) tenant | [2026-09-29](https://www.datacenterdynamics.com/en/news/crusoe-files-for-two-more-data-centers-at-goodnight-campus-in-armstrong-county-texas/) |
| Meta Prometheus | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | New Albany, OH | 1000 | Under construction | 2026 | n/a | [META](https://supercyclehq.com/stock/meta-platforms.md) operator; [VST](https://supercyclehq.com/stock/vistra-energy.md) power | [2026-01-09](https://about.fb.com/news/2026/01/meta-nuclear-energy-projects-power-american-ai-leadership/) |
| Meta El Paso Data Center | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | El Paso, TX | 1000 | Under construction | 2028 | 10 | [META](https://supercyclehq.com/stock/meta-platforms.md) operator; BLK investor | [2026-07-28](https://about.fb.com/news/2026/07/meta-announces-new-venture-with-blackrock-to-develop-data-center-in-el-paso/) |
| xAI Colossus 2 (Macrohard) | xAI (SpaceXAI) | Memphis, TN | 1000 | Partially operational | n/a | n/a | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips; [TSLA](https://supercyclehq.com/stock/tesla.md) equipment | [2026-08-01](https://en.wikipedia.org/wiki/Colossus_(data_center)) |
| Google Meitner Campus | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Gray and Roberts Counties, TX | 1000 | Under construction | n/a | n/a | [GOOGL](https://supercyclehq.com/stock/alphabet.md) operator | [2026-06-04](https://www.powermag.com/google-launches-1-gw-plus-co-located-data-center-and-generation-complex-in-texas-panhandle/) |
| Google Van Buren Township Campus (Project Cannoli) | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Van Buren Township, MI | 1000 | Under construction | late 2027 | n/a | [GOOGL](https://supercyclehq.com/stock/alphabet.md) operator | [2026-10-15](https://www.wxyz.com/news/van-buren-township-residents-frustrated-by-construction-tied-to-google-data-center-project) |
| Meta Lebanon Data Center | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Lebanon, IN | 1000 | Under construction | 2028 | 10 | [META](https://supercyclehq.com/stock/meta-platforms.md) operator | [2026-02-11](https://www.datacenterknowledge.com/data-center-construction/meta-breaks-ground-on-1-gw-indiana-data-center) |
| Beacon Point | Hut 8 ([HUT](https://supercyclehq.com/stock/hut-8.md)) | Nueces County, TX | 1000 | Under construction | n/a | 4.25 | [HUT](https://supercyclehq.com/stock/hut-8.md) operator; [J](https://supercyclehq.com/stock/jacobs-solutions.md) builder; [NVDA](https://supercyclehq.com/stock/nvidia.md) tenant | [2026-07-20](https://hut8.com/news-insights/press-releases/hut-8-fully-commercializes-1-gw-beacon-point-ai-data-center-campus-with-second-352-mw-it-lease) |
| Muskie Data Campus | TeraWulf ([WULF](https://supercyclehq.com/stock/terawulf.md)) | Grayson, KY | 1000 | Announced | 2028 | n/a | [WULF](https://supercyclehq.com/stock/terawulf.md) operator; [AEP](https://supercyclehq.com/stock/american-electric-power.md) power | [2026-05-26](https://investors.terawulf.com/news-events/press-releases/detail/141/terawulf-expands-infrastructure-platform-with-acquisition-of-1-gw-eastern-kentucky-hpc-campus) |
| Childress AI Data Center Campus | Crusoe and Lancium | Childress, TX | 1000 | Announced | 2026-Q3 | n/a | n/a | [2026-07-15](https://crusoe.ai/resources/newsroom/crusoe-and-lancium-announce-1-gigawatt-ai-data-center-campus-in-childress-texas) |
| Corsicana AI Campus | Riot Platforms ([RIOT](https://supercyclehq.com/stock/riot-platforms.md)) | Corsicana, TX | 1000 | Announced | n/a | n/a | [RIOT](https://supercyclehq.com/stock/riot-platforms.md) operator | [2026-08-10](https://blockspace.media/news/riot-platforms-signs-9-1b-191-mw-ai-lease-at-rockdale-loi-for-1-gw-corsicana/) |
| Colchis | Cipher Mining ([CIFR](https://supercyclehq.com/stock/cipher-mining.md)) | Tom Green County, TX | 1000 | Announced | 2028 | n/a | [CIFR](https://supercyclehq.com/stock/cipher-mining.md) operator; [AEP](https://supercyclehq.com/stock/american-electric-power.md) power | [2026-09-16](https://247wallst.com/investing/2026/09/16/cipher-digital-surges-9-on-conditional-ercot-status-for-3-2-gw-of-texas-capacity-core-scientific-rises-4-iren-nudges-higher/) |
| Taylor Technology Campus | Big Watt Digital and PowerHouse Data Centers | Taylor, TX | 1000 | Announced | 2028-H1 | n/a | n/a | [2026-10-08](https://www.datacenterdynamics.com/en/news/powerhouse-big-watt-secure-approval-for-1gw-behind-the-meter-campus-in-taylor-texas/) |
| Stargate UAE | G42 | Abu Dhabi, United Arab Emirates | 1000 | Under construction | Q3 2026 | n/a | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips; [ORCL](https://supercyclehq.com/stock/oracle.md) tenant; [CSCO](https://supercyclehq.com/stock/cisco-systems.md) networking; [SFTBY](https://supercyclehq.com/stock/softbank-group.md) partner | [2025-12-05](https://www.thenationalnews.com/business/2025/12/05/stargate-uaes-first-phase-to-be-completed-in-third-quarter-of-2026/) |
| Google India AI Hub (Visakhapatnam) | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Visakhapatnam, India | 1000 | Under construction | 2026-2030 rollout | 15 | [GOOGL](https://supercyclehq.com/stock/alphabet.md) operator | [2026-04-28](https://www.googlecloudpresscorner.com/2026-04-28-Google-Breaks-Ground-on-India-AI-Hub,-Launching-a-National-Industrial-Ecosystem-Alongside-Indias-Digital-Infrastructure-Milestone) |
| Reliance Intelligence Jamnagar AI Data Center | Reliance Industries | Jamnagar, Gujarat, India | 1000 | Under construction | end of 2026 (first 120MW) | n/a | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips; [META](https://supercyclehq.com/stock/meta-platforms.md) tenant | [2026-06-10](https://www.pv-magazine-india.com/2026/06/10/reliance-meta-to-develop-168-mw-ai-data-centre-powered-by-renewable-energy-in-jamnagar/) |
| Meta Sturgeon Data Centre | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Sturgeon County, Alberta, Canada | 1000 | Under construction | n/a | 9.2 | [META](https://supercyclehq.com/stock/meta-platforms.md) operator; [PBA](https://supercyclehq.com/stock/pembina-pipeline.md) power | [2026-07-09](https://www.cbc.ca/news/canada/edmonton/meta-data-centre-sturgeon-county-alberta-9.7263271) |
| TCS HyperVault AI Data Center Campus | HyperVault (Tata Consultancy Services) | Hyderabad, Telangana, India | 1000 | Announced | n/a | n/a | TPG investor | [2026-09-05](https://www.bloomberg.com/news/articles/2026-09-05/tcs-plans-one-gigawatt-capacity-data-center-in-southern-india) |
| Cottam AI Data Centre Campus | Tritax Management | Cottam, Nottinghamshire, England, United Kingdom | 1000 | Announced | 2030 | n/a | n/a | [2025-09-15](https://www.edfenergy.com/media-centre/holtec-international-edf-uk-and-tritax-announce-plans-develop-cottam-site-data-centres-and) |
| Era4 The Mill (Newport AI Campus) | Era4 | Newport, Wales, United Kingdom | 1000 | Announced | n/a | n/a | n/a | [2026-10-22](https://datacenterdynamics.com/en/news/era4-reveals-details-of-hyperscale-data-center-planned-for-former-steelworks-in-newport-wales) |
| AWS Susquehanna Campus (Cumulus) | Amazon Web Services ([AMZN](https://supercyclehq.com/stock/amazon.md)) | Salem Township, PA | 960 | Partially operational | n/a | 20 | [AMZN](https://supercyclehq.com/stock/amazon.md) operator; [TLN](https://supercyclehq.com/stock/talen-energy.md) power | [2026-08-01](https://www.talenenergy.com/powering-data/) |
| Apollo | Cipher Digital ([CIFR](https://supercyclehq.com/stock/cipher-mining.md)) | Near San Antonio, TX | 900 | Announced | n/a | n/a | [CIFR](https://supercyclehq.com/stock/cipher-mining.md) operator | [2026-08-04](https://www.stocktitan.net/news/CIFR/) |
| Helios | Galaxy Digital ([GLXY](https://supercyclehq.com/stock/galaxy-digital.md)) | Dickens County, TX | 800 | Partially operational | n/a | n/a | [GLXY](https://supercyclehq.com/stock/galaxy-digital.md) operator; [CRWV](https://supercyclehq.com/stock/coreweave.md) tenant | [2026-07-06](https://www.galaxy.com/insights/press-releases) |
| Google Pine Island Data Center | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Pine Island, MN | 780 | Announced | n/a | n/a | [GOOGL](https://supercyclehq.com/stock/alphabet.md) operator | [2026-02-24](https://blog.google/innovation-and-ai/infrastructure-and-cloud/global-network/data-center-pine-island/) |
| Childress Campus (Horizon) | IREN ([IREN](https://supercyclehq.com/stock/iris-energy.md)) | Childress, TX | 750 | Partially operational | 2027 | n/a | [IREN](https://supercyclehq.com/stock/iris-energy.md) operator; [MSFT](https://supercyclehq.com/stock/microsoft.md) tenant; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips; [DELL](https://supercyclehq.com/stock/dell-technologies.md) equipment | [2026-08-13](https://www.stocktitan.net/news/IREN/) |
| BDx AI Campus 2 (CGK4) | BDx Data Centers | Jatiluhur, Purwakarta, West Java, Indonesia | 640 | Announced | 2027 | n/a | n/a | [2026-10-02](https://www.dealstreetasia.com/stories/indonesia-halts-bdx-data-centre-project-due-to-lack-of-permits-496721/) |
| Nexus Hubbard Campus | Nexus Data Centers | Hubbard, TX | 600 | Under construction | 2027-10 | 16 | [GOOGL](https://supercyclehq.com/stock/alphabet.md) backstop | [2026-08-19](https://www.bloomberg.com/news/articles/2026-08-19/anthropic-tied-data-center-inks-1-3-billion-private-credit-loan) |
| Sesterce Jämsä Campus | Sesterce | Jämsä, Finland | 600 | Announced | n/a | n/a | n/a | [2026-10-08](https://www.datacenterdynamics.com/en/news/sesterce-to-invest-10bn-in-600mw-ai-data-center-campus-in-j%C3%A4ms%C3%A4-finland) |
| Pure DC Seinajoki Campus (SJK01) | Pure Data Centres Group | Seinäjoki, Finland | 550 | Under construction | n/a | n/a | [MSFT](https://supercyclehq.com/stock/microsoft.md) tenant | [2026-07-14](https://www.datacenterdynamics.com/en/news/microsoft-signs-on-for-capacity-at-pure-dc-data-center-in-finland-report/) |
| Apatura Ravenscraig AI Energy Campus | Apatura | Ravenscraig, North Lanarkshire, Scotland, United Kingdom | 550 | Announced | 2030 | n/a | n/a | [2026-09-21](https://consult.apatura.energy/ravenscraig/the-project) |
| Project Caprock | Aligned Data Centers | Texas | 540 | Under construction | n/a | n/a | n/a | [2026-04-13](https://w.media/project-caprock-aligned-data-centers-breaks-ground-on-540-mw-dc-campus-in-texas/) |
| Logan Prairie | Hut 8 ([HUT](https://supercyclehq.com/stock/hut-8.md)) | Latham, IL | 500 | Announced | n/a | 5 | [HUT](https://supercyclehq.com/stock/hut-8.md) operator | [2026-07-31](https://blockspace.media/insight/hut-8-illinois-data-center-stalls/) |
| Bell AI Fabric | Bell Canada (BCE) ([BCE](https://supercyclehq.com/stock/bce.md)) | British Columbia, Canada (Kamloops, Merritt and other sites) | 500 | Under construction | 2026 (first facility) | n/a | [BCE](https://supercyclehq.com/stock/bce.md) operator | [2026-01-01](https://www.castanetkamloops.net/news/Kamloops/620383/Bell-Cohere-sign-deal-to-operate-models-using-Bell-AI-Fabric-infrastructure) |
| YTL AI Cloud (YTL Green Data Center Park) | YTL Power International | Kulai, Johor, Malaysia | 500 | Partially operational | 2027 | 2.36 | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2025-07-29](https://www.datacenterdynamics.com/en/news/ytl-power-and-nvidia-to-invest-23bn-in-ai-infrastructure-in-malaysia/) |
| Khazna-Eni Ferrera Erbognone AI Campus | Khazna Data Centers | Ferrera Erbognone, Lombardy, Italy | 500 | Announced | n/a | n/a | E power | [2026-08-10](https://www.eunews.it/en/2026/08/10/eu-commission-approves-khazna-eni-joint-venture-says-it-does-not-raise-competition-concerns/) |
| Ardian-Verne Île-de-France Campus | Verne | Île-de-France, France | 500 | Announced | 2030 | n/a | n/a | [2026-06-01](https://datacentremagazine.com/news/ardian-and-verne-plan-500mw-ai-data-centre-hub-in-5bn-deal) |
| Lake Mariner | TeraWulf ([WULF](https://supercyclehq.com/stock/terawulf.md)) | Barker, NY | 438 | Partially operational | 2027 | n/a | [WULF](https://supercyclehq.com/stock/terawulf.md) operator; [GOOGL](https://supercyclehq.com/stock/alphabet.md) backstop; [GOOGL](https://supercyclehq.com/stock/alphabet.md) tenant | [2026-08-05](https://investors.terawulf.com/news-events/press-releases/detail/144/terawulf-reports-second-quarter-2026-results) |
| Delta Forge 1 | Applied Digital ([APLD](https://supercyclehq.com/stock/applied-digital.md)) | Boyce, LA | 430 | Under construction | 2027 | n/a | [APLD](https://supercyclehq.com/stock/applied-digital.md) operator | [2026-07-27](https://ir.applieddigital.com/news-events/press-releases/detail/159/applied-digital-reports-fiscal-fourth-quarter-and-full-year) |
| Justified Data Campus | TeraWulf ([WULF](https://supercyclehq.com/stock/terawulf.md)) | Hawesville, KY | 401 | Under construction | 2028 | 19 | [WULF](https://supercyclehq.com/stock/terawulf.md) operator | [2026-07-06](https://investors.terawulf.com/news-events/press-releases/detail/142/terawulf-announces-anthropic-lease-at-justified-data-campus-and-sale-of-majority-interest-in-abernathy-joint-venture-to-fluidstack) |
| Polaris Forge 1 | Applied Digital ([APLD](https://supercyclehq.com/stock/applied-digital.md)) | Ellendale, ND | 400 | Partially operational | n/a | 1.59 | [APLD](https://supercyclehq.com/stock/applied-digital.md) operator; [CRWV](https://supercyclehq.com/stock/coreweave.md) tenant | [2026-10-02](https://datacenterdynamics.com/en/news/applied-digital-adds-75mw-of-capacity-at-ellendale-data-center-campus-in-north-dakota) |
| JERA-RHAELM Chiba AI Data Center | RHAELM | Chiba, Japan | 400 | Announced | 2029 | 15 | [DELL](https://supercyclehq.com/stock/dell-technologies.md) equipment | [2026-10-01](https://datacentremagazine.com/news/inside-dells-mou-to-build-ai-infrastructure-with-jera) |
| HyperDC MBL1 | HyperDC | Moorabool, Victoria, Australia | 400 | Announced | n/a | n/a | n/a | [2026-10-09](https://www.datacenterdynamics.com/en/news/plans-filed-for-400mw-data-center-campus-outside-melbourne-australia) |
| Oxagon AI Data Center (NEOM) | Humain and DataVolt | Oxagon, NEOM, Saudi Arabia | 360 | Under construction | 2028 | n/a | n/a | [2026-08-31](https://www.datacenterdynamics.com/en/news/humain-breaks-ground-on-neoms-oxagon-data-center/) |
| Vineland Data Center | Nebius ([NBIS](https://supercyclehq.com/stock/nebius-group.md)) | Vineland, NJ | 350 | Under construction | n/a | n/a | [NBIS](https://supercyclehq.com/stock/nebius-group.md) operator; [MSFT](https://supercyclehq.com/stock/microsoft.md) tenant | [2026-08-18](https://whyy.org/articles/vineland-planning-board-approves-data-center-plan/) |
| Nebius Lappeenranta AI Factory | Nebius ([NBIS](https://supercyclehq.com/stock/nebius-group.md)) | Lappeenranta, Finland | 310 | Announced | 2027 | 10 | [NBIS](https://supercyclehq.com/stock/nebius-group.md) operator; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-03-31](https://nebius.com/newsroom/nebius-to-construct-310-mw-ai-factory-in-finland) |
| Polaris Forge 3 | Applied Digital ([APLD](https://supercyclehq.com/stock/applied-digital.md)) | North Dakota | 300 | Under construction | 2027-08 | n/a | [APLD](https://supercyclehq.com/stock/applied-digital.md) operator | [2026-05-20](https://ir.applieddigital.com/news-events/press-releases/detail/152/applied-digital-reaches-significant-milestone-surpassing-1) |
| Black Pearl | Cipher Digital ([CIFR](https://supercyclehq.com/stock/cipher-mining.md)) | Texas | 300 | Partially operational | n/a | n/a | [CIFR](https://supercyclehq.com/stock/cipher-mining.md) operator; [AMZN](https://supercyclehq.com/stock/amazon.md) tenant | [2026-08-04](https://www.stocktitan.net/news/CIFR/) |
| Lancaster Campus | CoreWeave ([CRWV](https://supercyclehq.com/stock/coreweave.md)) | Lancaster County, PA | 300 | Under construction | n/a | 6 | [CRWV](https://supercyclehq.com/stock/coreweave.md) operator | [2025-07-15](https://www.datacenterdynamics.com/en/news/coreweave-plans-6bn-data-center-in-lancaster-pennsylvania/) |
| NFD Korea Dangjin Campus | NFD Korea (with EFD Co.) | Dangjin, Chungcheongnam-do, South Korea | 300 | Announced | 2028-01 | n/a | n/a | [2026-09-09](https://www.datacenterdynamics.com/en/news/data-center-company-nfd-korea-to-build-300mw-campus-south-of-seoul/) |
| PPC Kozani AI Data Center (Agios Dimitrios) | Public Power Corporation (PPC) | Kozani, Western Macedonia, Greece | 300 | Announced | 2028 | n/a | [AMZN](https://supercyclehq.com/stock/amazon.md) tenant | [2026-09-17](https://balkangreenenergynews.com/ppc-signs-deal-with-amazon-to-develop-300-mw-data-center/) |
| Apatura Westerhill AI Energy Campus | Apatura | Westerhill Regeneration Area, East Dunbartonshire, Scotland, United Kingdom | 300 | Announced | n/a | n/a | n/a | [2026-09-21](https://consult.apatura.energy/westerhill/the-project) |
| Kenilworth Campus | CoreWeave ([CRWV](https://supercyclehq.com/stock/coreweave.md)) | Kenilworth, NJ | 250 | Under construction | 2027 | 1.8 | [CRWV](https://supercyclehq.com/stock/coreweave.md) operator | [2025-11-25](https://re-nj.com/coreweave-begins-1-8-billion-data-center-project-in-kenilworth/) |
| River Bend | Hut 8 ([HUT](https://supercyclehq.com/stock/hut-8.md)) | West Feliciana Parish, LA | 245 | Under construction | n/a | 10 | [HUT](https://supercyclehq.com/stock/hut-8.md) operator; [GOOGL](https://supercyclehq.com/stock/alphabet.md) backstop; [J](https://supercyclehq.com/stock/jacobs-solutions.md) builder | [2025-12-17](https://www.prnewswire.com/news-releases/hut-8-signs-15-year-245-mw-ai-data-center-lease-at-river-bend-campus-with-total-contract-value-of-7-0-billion-302383000.html) |
| Phoenix Campus | Prime Data Centers | Phoenix, AZ | 240 | Partially operational | n/a | 2 | n/a | [2026-05-21](https://www.citybiz.co/article/prime-data-centers-launches-first-phase-of-240mw-phoenix-campus-as-ai-infrastructure-demand-accelerates/) |
| Stargate Norway | Nscale / Aker (50-50 JV) | Kvandal, Narvik, Norway | 230 | Under construction | end of 2026 (first 100,000 GPUs) | 1 | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips; [MSFT](https://supercyclehq.com/stock/microsoft.md) tenant | [2026-04-15](https://www.cnbc.com/2026/04/15/openai-stargate-norway-project-microsoft.html) |
| Campus Campinas (Terranova) | Terranova (Actis) | Campinas, São Paulo, Brazil | 216 | Under construction | 2027-12 | 0.5 | n/a | [2026-08-20](https://www.datacenterdynamics.com/en/news/terranova-boosts-technology-infrastructure-with-the-construction-of-one-of-latin-americas-first-ai-data-centers/) |
| Delta Forge 2 | Applied Digital ([APLD](https://supercyclehq.com/stock/applied-digital.md)) | Brookwood, Tuscaloosa County, AL | 210 | Announced | 2028-Q1 | 3.2 | [APLD](https://supercyclehq.com/stock/applied-digital.md) operator | [2026-09-25](https://www.fox10tv.com/2026/09/25/applied-digital-confirms-32-billion-data-center-campus-brookwood/) |
| Barber Lake | Cipher Digital ([CIFR](https://supercyclehq.com/stock/cipher-mining.md)) | West Texas, TX | 207 | Under construction | n/a | 1.4 | [CIFR](https://supercyclehq.com/stock/cipher-mining.md) operator; [GOOGL](https://supercyclehq.com/stock/alphabet.md) backstop | [2025-09-25](https://www.globenewswire.com/news-release/2025/09/25/3156091/0/en/Cipher-Mining-Signs-168-MW-10-Year-AI-Hosting-Agreement-with-Fluidstack.html) |
| Polaris Forge 2 | Applied Digital ([APLD](https://supercyclehq.com/stock/applied-digital.md)) | Harwood, ND | 200 | Under construction | n/a | 3 | [APLD](https://supercyclehq.com/stock/applied-digital.md) operator | [2026-07-27](https://ir.applieddigital.com/news-events/press-releases/detail/159/applied-digital-reports-fiscal-fourth-quarter-and-full-year) |
| Fort Worth Campus | CyrusOne | Fort Worth, TX | 200 | Announced | n/a | n/a | n/a | [2026-01-13](https://www.prnewswire.com/news-releases/cyrusone-and-eolian-partner-to-enable-rapid-deployment-of-200-megawatt-data-center-campus-in-fort-worth-texas-302349000.html) |
| Humain AI Factories (Riyadh and Dammam) | Humain | Riyadh and Dammam, Saudi Arabia | 200 | Partially operational | 2030 | n/a | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips; [AMD](https://supercyclehq.com/stock/advanced-micro-devices.md) chips; [CSCO](https://supercyclehq.com/stock/cisco-systems.md) networking | [2026-09-19](https://www.constructionreviewonline.com/news-2/mis-wins-2-33bn-design-build-contract-for-humain-ai-data-center-expansion-in-saudi-arabia/) |
| Microsoft-G42 Khazna UAE Expansion | Khazna Data Centers (G42) | United Arab Emirates | 200 | Under construction | 2026 | 15.2 | [MSFT](https://supercyclehq.com/stock/microsoft.md) tenant; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2025-11-01](https://news.microsoft.com/source/emea/2025/11/microsoft-and-g42-accelerate-uaes-digital-future-with-major-data-centre-expansion/) |
| ByteDance Pecém Data Center | ByteDance | Pecém, Ceará, Brazil | 200 | Under construction | 2027 | 38.4 | n/a | [2026-05-19](https://www.datacenterdynamics.com/en/news/omnia-signs-2bn-wind-energy-deal-with-casa-dos-ventos-to-power-bytedance-data-center-in-brazil-report/) |
| Africa Data Centers Egypt (Vodafone, Elsewedy, Cassava) | Africa Data Centers Egypt | Egypt | 200 | Announced | n/a | n/a | VOD operator; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-09-08](https://techafricanews.com/2026/09/08/egypt-vodafone-elsewedy-cassava-1bn-data-centre/) |
| Rockdale AI Data Center | Riot Platforms ([RIOT](https://supercyclehq.com/stock/riot-platforms.md)) | Rockdale, TX | 191 | Under construction | n/a | n/a | [RIOT](https://supercyclehq.com/stock/riot-platforms.md) operator; [AMD](https://supercyclehq.com/stock/advanced-micro-devices.md) chips | [2026-08-10](https://www.cnbc.com/2026/08/11/riot-platforms-anthropic-ai-data-center-deal.html) |
| Anthropic Abernathy Campus | Fluidstack | Abernathy, TX | 168 | Under construction | 2026 | n/a | n/a | [2026-07-06](https://investors.terawulf.com/news-events/press-releases/detail/142/terawulf-announces-anthropic-lease-at-justified-data-campus-and-sale-of-majority-interest-in-abernathy-joint-venture-to-fluidstack) |
| Compute Nordic Finland AI Data Centre (Mikkeli) | Compute Nordic Finland | Mikkeli, Finland | 165 | Under construction | n/a | n/a | [CBRS](https://supercyclehq.com/stock/cerebras.md) tenant | [2026-08-31](https://investors.cerebras.ai/news-releases/news-release-details/cerebras-and-compute-nordic-finland-announce-new-165-mw-ai-data) |
| SoftBank Sakai AI Data Center | SoftBank Corp ([SFTBY](https://supercyclehq.com/stock/softbank-group.md)) | Sakai, Osaka, Japan | 150 | Under construction | 2026 | n/a | [SFTBY](https://supercyclehq.com/stock/softbank-group.md) operator | [2025-03-01](https://www.datacenterdynamics.com/en/news/softbank-buys-former-sharp-factory-for-676m-to-build-ai-data-center-in-osaka-japan/) |
| Bitdeer Tydal Campus | Bitdeer AI ([BTDR](https://supercyclehq.com/stock/bitdeer-technologies.md)) | Tydal, Norway | 121 | Under construction | 2026-12 | n/a | [BTDR](https://supercyclehq.com/stock/bitdeer-technologies.md) operator; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-08-04](https://www.sec.gov/Archives/edgar/data/0001899123/000121390026072867/ea029623001ex99-1.htm) |
| SK-AWS Ulsan AI Data Center | SK Telecom / SK Group with AWS ([SKM](https://supercyclehq.com/stock/sk-telecom.md)) | Ulsan, South Korea | 103 | Under construction | November 2027 (first 41MW) | 5.11 | [SKM](https://supercyclehq.com/stock/sk-telecom.md) operator; [AMZN](https://supercyclehq.com/stock/amazon.md) tenant | [2025-09-01](https://www.datacenterdynamics.com/en/news/sk-group-and-aws-break-ground-for-data-center-in-ulsan-korea/) |
| Hon Hai Kaohsiung Super Computing Center | Foxconn (Hon Hai) | Kaohsiung, Taiwan | 100 | Partially operational | 2026 | n/a | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2025-05-20](https://www.cnbc.com/2025/05/20/taiwans-foxconn-ai-data-center-with-nvidia-to-have-100-mw-of-power.html) |
| EverWind Point Tupper Campus | EverWind | Point Tupper, Nova Scotia, Canada | 95 | Announced | 2027 | 7.1 | n/a | [2026-10-16](https://www.cp24.com/news/canada/2026/10/16/everwind-says-10b-ai-data-centre-proposal-largest-private-investment-in-ns-history/) |
| Stingray | Cipher Digital ([CIFR](https://supercyclehq.com/stock/cipher-mining.md)) | Texas | 70 | Under construction | n/a | 0.81 | [CIFR](https://supercyclehq.com/stock/cipher-mining.md) operator; [AMZN](https://supercyclehq.com/stock/amazon.md) tenant | [2026-06-08](https://www.stocktitan.net/news/CIFR/) |
| Nebius Mantsala Expansion (Second Data Center) | Nebius ([NBIS](https://supercyclehq.com/stock/nebius-group.md)) | Mantsala, Finland | 70 | Announced | 2027 | n/a | [NBIS](https://supercyclehq.com/stock/nebius-group.md) operator; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-08-13](https://www.datacenterdynamics.com/en/news/nebius-expands-european-presence-announces-deployment-in-estonia-and-second-data-center-in-m%C3%A4nts%C3%A4l%C3%A4-finland/) |
| Bitdeer AI A901 | Bitdeer AI ([BTDR](https://supercyclehq.com/stock/bitdeer-technologies.md)) | Malaysia | 67 | Announced | 2027-06 | n/a | [BTDR](https://supercyclehq.com/stock/bitdeer-technologies.md) operator; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-10-08](https://www.datacenterdynamics.com/en/news/bitdeer-ai-signs-67mw-ai-cloud-agreement-in-malaysia) |
| Yotta Nvidia Blackwell Supercluster (Greater Noida) | Yotta Data Services | Greater Noida, India | 60 | Under construction | August 2026 | 2 | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-02-27](https://www.cnbc.com/2026/02/27/india-yotta-nvidia-ai-gpu-demand-data-centers-investment.html) |
| Nscale Loughton AI Campus (Microsoft UK Supercomputer) | Nscale | Loughton, Essex, United Kingdom | 50 | Under construction | n/a | n/a | n/a | [2026-10-18](https://www.datacenterdynamics.com/en/news/microsoft-pulls-out-of-delayed-nscale-data-center-in-loughton-essex/) |
| Nscale Glomfjord AI Data Centre | Nscale | Glomfjord, Norway | 30 | Partially operational | n/a | n/a | [MSFT](https://supercyclehq.com/stock/microsoft.md) tenant; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-06-03](https://time.com/article/2026/06/03/ai-norway-nscale-data-center/) |
| Microsoft Fairwater Mount Pleasant | Microsoft ([MSFT](https://supercyclehq.com/stock/microsoft.md)) | Mount Pleasant, WI | n/a | Partially operational | 2028 | 4.7 | [MSFT](https://supercyclehq.com/stock/microsoft.md) operator; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-06-23](https://news.microsoft.com/source/2026/06/23/microsoft-completes-construction-on-first-datacenter-facility-in-mount-pleasant-wisconsin/) |
| Microsoft Fairwater Atlanta | Microsoft ([MSFT](https://supercyclehq.com/stock/microsoft.md)) | Atlanta, GA | n/a | Operational | n/a | n/a | [MSFT](https://supercyclehq.com/stock/microsoft.md) operator; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2025-11-12](https://news.microsoft.com/source/features/ai/from-wisconsin-to-atlanta-microsoft-connects-datacenters-to-build-its-first-ai-superfactory/) |
| xAI Colossus 1 | xAI (SpaceXAI) | Memphis, TN | n/a | Operational | n/a | n/a | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips; [TSLA](https://supercyclehq.com/stock/tesla.md) equipment; [DELL](https://supercyclehq.com/stock/dell-technologies.md) equipment | [2026-08-01](https://en.wikipedia.org/wiki/Colossus_(data_center)) |
| xAI MACROHARDRR Southaven | xAI (SpaceXAI) | Southaven, MS | n/a | Under construction | 2026 | 20 | [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-01-08](https://governorreeves.ms.gov/tech-leader-xai-investing-more-than-20-billion-in-southaven/) |
| Google Haskell County Campus | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Haskell County, TX | n/a | Under construction | n/a | 40 | [GOOGL](https://supercyclehq.com/stock/alphabet.md) operator | [2026-06-04](https://www.powermag.com/google-launches-1-gw-plus-co-located-data-center-and-generation-complex-in-texas-panhandle/) |
| Google Council Bluffs Campus | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Council Bluffs, IA | n/a | Operational | n/a | 7 | [GOOGL](https://supercyclehq.com/stock/alphabet.md) operator | [2026-08-01](https://datacenters.google/locations/) |
| Stargate Lordstown | SoftBank | Lordstown, OH | n/a | Under construction | n/a | n/a | n/a | [2026-04-17](https://epoch.ai/publications/openai-stargate-where-the-us-sites-stand) |
| AWS Shreveport Campus (Resilient Technology Park) | Amazon Web Services ([AMZN](https://supercyclehq.com/stock/amazon.md)) | Shreveport, LA | n/a | Announced | late 2027 to early 2028 | 6 | [AMZN](https://supercyclehq.com/stock/amazon.md) operator | [2026-08-18](https://www.datacenterdynamics.com/en/news/aws-pledges-6bn-investment-in-data-center-campus-in-shreveport-louisiana/) |
| AWS GW Ranch | Amazon Web Services ([AMZN](https://supercyclehq.com/stock/amazon.md)) | Pecos County, TX | n/a | Announced | n/a | n/a | [AMZN](https://supercyclehq.com/stock/amazon.md) operator | [2026-08-10](https://www.enr.com/articles/63464-amazon-discloses-ownership-of-gw-ranch-giant-texas-data-center-gas-power-complex) |
| Project Clydesdale | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Tulsa County, OK | n/a | Under construction | n/a | n/a | [GOOGL](https://supercyclehq.com/stock/alphabet.md) operator | [2026-08-19](https://tulsachamber.com/news/2026/08/19/economic-development/google-to-operate-tulsa-county-data-center/) |
| Meta Mason County Campus (Maysville) | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Mason County, KY | n/a | Announced | n/a | 10 | [META](https://supercyclehq.com/stock/meta-platforms.md) operator | [2026-10-16](https://www.fox19.com/2026/10/16/meta-revealed-partner-2000-acre-nky-data-center-residents-pushback/) |
| Panther Creek | Keel Infrastructure ([KEEL](https://supercyclehq.com/stock/keel-infrastructure.md)) | Nesquehoning, PA | n/a | Under construction | n/a | n/a | [KEEL](https://supercyclehq.com/stock/keel-infrastructure.md) operator; [PPL](https://supercyclehq.com/stock/ppl.md) power | [2026-02-25](https://blockspace.media/news/local-officials-greenlight-bitfarms-panther-creek-ai-data-center/) |
| Denton Campus | Core Scientific ([CORZ](https://supercyclehq.com/stock/core-scientific.md)) | Denton, TX | n/a | Operational | n/a | n/a | [CORZ](https://supercyclehq.com/stock/core-scientific.md) operator; [CRWV](https://supercyclehq.com/stock/coreweave.md) tenant; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2026-01-13](https://www.datacenterdynamics.com/en/news/coreweave-deploys-16000-gpus-at-delayed-data-center-in-denton-texas/) |
| AWS-Humain AI Zone | Amazon Web Services / Humain ([AMZN](https://supercyclehq.com/stock/amazon.md)) | Saudi Arabia | n/a | Announced | 2026 | 5 | [AMZN](https://supercyclehq.com/stock/amazon.md) operator | [2025-05-13](https://www.aboutamazon.com/news/company-news/amazon-aws-humain-ai-investment-in-saudi-arabia) |
| Telus Sovereign AI Factory (Rimouski) | Telus ([TU](https://supercyclehq.com/stock/telus.md)) | Rimouski, Quebec, Canada | n/a | Operational | n/a | n/a | [TU](https://supercyclehq.com/stock/telus.md) operator; [NVDA](https://supercyclehq.com/stock/nvidia.md) chips | [2025-09-24](https://betakit.com/telus-opens-inaugural-sovereign-ai-factory-in-rimouski/) |

## Power deals

| Date | Buyer | Supplier | Capacity (MW) | Technology | Status | Project | Source |
| --- | --- | --- | --- | --- | --- | --- | --- |
| 2026-10-06 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Constellation Energy ([CEG](https://supercyclehq.com/stock/constellation-energy.md)) | 890 | Nuclear uprate | signed | 11 Constellation nuclear units, Illinois, Pennsylvania and New Jersey (PJM) | [2026-10-06](https://www.powermag.com/google-deal-backs-890-mw-of-constellation-nuclear-uprates-at-11-pjm-reactors/) |
| 2026-10-02 | Oracle ([ORCL](https://supercyclehq.com/stock/oracle.md)) | We Energies ([WEC](https://supercyclehq.com/stock/wec-energy-group.md)) | n/a | Existing nuclear PPA | signed | Point Beach Nuclear Plant, Wisconsin, for Project Lighthouse (Port Washington) | [2026-10-02](https://wisconsinwatch.org/2026/10/wisconsin-we-energies-deal-oracle-data-center-nuclear-energy-power-point-beach-plant/) |
| 2026-09-30 | Amazon ([AMZN](https://supercyclehq.com/stock/amazon.md)) | Constellation Energy ([CEG](https://supercyclehq.com/stock/constellation-energy.md)) | 190 | Nuclear uprate | signed | Calvert Cliffs Nuclear Power Plant, Maryland | [2026-09-30](https://www.constellationenergy.com/news/2026/09/constellation-and-amazon-announce-20-year-power-purchase-agreement-at-calvert-cliffs.html) |
| 2026-09-21 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Georgia Power ([SO](https://supercyclehq.com/stock/southern-company.md)) | 96 | Nuclear uprate | signed | Plant Vogtle and Plant Hatch nuclear uprates, Georgia | [2026-09-21](https://www.prnewswire.com/news-releases/georgia-power-agreement-with-google-to-provide-approximately-900-million-in-projected-benefits-for-customers-and-advance-nuclear-energy-in-georgia-302885197.html) |
| 2026-09-16 | Amazon ([AMZN](https://supercyclehq.com/stock/amazon.md)) | Generac Holdings ([GNRC](https://supercyclehq.com/stock/generac-holdings.md)) | n/a | Backup generators | signed | Amazon data center backup power, site undisclosed | [2026-09-16](https://www.cnbc.com/2026/09/16/amazon-obtains-right-to-buy-up-to-340m-of-generac-boosting-stock-.html) |
| 2026-09-16 | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Apex Clean Energy | 144 | Solar | signed | Starling Solar, Gonzales County, Texas | [2026-09-16](https://www.utilitydive.com/news/meta-apex-clean-energy-144-mw-texas-solar-ppa/830675/) |
| 2026-09-16 | NAVER | Gurin Energy | 216 | Solar | letter-of-intent | Jindo Green Solar, South Korea | [2026-09-16](https://en.sedaily.com/technology/2026/09/16/naver-signs-solar-deal-to-power-ai-data-centers) |
| 2026-09-09 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Fortum | n/a | Existing nuclear PPA | signed | Loviisa Nuclear Power Plant, Finland | [2026-09-11](https://www.ans.org/news/2026-09-11/article-8381/in-a-boost-to-finlands-loviisa-plant-google-and-fortum-ink-nuclear-ppa/) |
| 2026-09-02 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | MN8 Energy | 86 | Solar + Storage | signed | Mammoth Solar, Kanawha County, West Virginia | [2026-09-02](https://www.globenewswire.com/news-release/2026/09/02/3355060/0/en/mn8-energy-google-and-eos-energy-enterprises-bring-advanced-clean-energy-solutions-to-west-virginia.html) |
| 2026-09-01 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Fervo Energy | 396 | Geothermal | signed | Cape Station GeoCluster, Beaver County, Utah | [2026-09-01](https://ir.fervoenergy.com/news-releases/news-release-details/fervo-energy-and-google-sign-396-mw-ppa) |
| 2026-08-28 | Amazon ([AMZN](https://supercyclehq.com/stock/amazon.md)) | OX2 / Mirova | 199 | Wind | signed | Boarp, Dallebo, Fagelas and Fagelasen wind farms, Sweden | [2026-08-28](https://www.datacenterdynamics.com/en/news/amazon-signs-199mw-worth-of-ppas-across-sweden-with-ox2-and-mirova/) |
| 2026-08-18 | QTS Data Centers | ENGIE | 48 | Solar | signed | Irving, Texas data center campus | [2026-08-18](https://www.datacenterdynamics.com/en/news/qts-signs-48mw-solar-ppa-with-engie-in-irving-texas/) |
| 2026-08-12 | Nebius Group ([NBIS](https://supercyclehq.com/stock/nebius-group.md)) | Bloom Energy ([BE](https://supercyclehq.com/stock/bloom-energy.md)) | 328 | Fuel cell | signed | New Jersey AI data center on-site power | [2026-08-12](https://247wallst.com/investing/2026/08/12/bloom-energy-jumps-13-as-nebius-picks-its-fuel-cells-for-ai-data-center/) |
| 2026-08-11 | Anthropic | ERock ([EROC](https://supercyclehq.com/stock/enchanted-rock.md)) | 470 | Natural gas | signed | RockBlock natural gas generator equipment order, site undisclosed | [2026-08-11](https://www.businesswire.com/news/home/20260811144024/en/ERock-Reports-Second-Quarter-2026-Results) |
| 2026-08-07 | Undisclosed hyperscaler | Energy Vault ([NRGV](https://supercyclehq.com/stock/energy-vault.md)) | 1250 | Natural gas | signed | Texas off-grid AI data center power infrastructure | [2026-08-10](https://www.datacenterdynamics.com/en/news/energy-vault-signs-125gw-power-supply-deal-with-texas-data-center-developer/) |
| 2026-08-04 | Undisclosed hyperscaler | NRG Energy ([NRG](https://supercyclehq.com/stock/nrg-energy.md)) | 1200 | Natural gas | signed | Texas data center power project | [2026-08-06](https://www.utilitydive.com/news/nrg-hyperscaler-data-center-texas-1200-mw/760000/) |
| 2026-07-30 | Crusoe Energy | Aalo Atomics | 10 | SMR | signed | Aalo-X reactor powering a Crusoe Spark modular data center at Idaho National Laboratory | [2026-07-30](https://www.powermag.com/aalo-crusoe-plan-2027-inl-demonstration-pairing-nuclear-power-and-ai-data-center-load/) |
| 2026-06-30 | Brookfield Asset Management (BAM) | Bloom Energy ([BE](https://supercyclehq.com/stock/bloom-energy.md)) | n/a | Fuel cell | signed | AI infrastructure power framework | [2026-07-09](https://www.power-eng.com/news/brookfield-bloom-energy-expand-partnership-to-25-billion-framework-for-onsite-data-center-power/) |
| 2026-06-24 | Fit Energy | FuelCell Energy ([FCEL](https://supercyclehq.com/stock/fuelcell-energy.md)) | 380 | Fuel cell | signed | Data center power supply agreement | [2026-06-25](https://www.datacenterdynamics.com/en/news/fuelcell-energy-signs-up-to-380mw-fuel-cell-supply-deal-with-fit-energy-to-power-data-center-operations/) |
| 2026-06-22 | Microsoft ([MSFT](https://supercyclehq.com/stock/microsoft.md)) | Chevron ([CVX](https://supercyclehq.com/stock/chevron.md)) | 2670 | Natural gas | signed | Project Kilby, West Texas | [2026-06-23](https://www.power-eng.com/gas/new-co-located-gas-plant-to-power-microsoft-data-center-in-west-texas/) |
| 2026-06-11 | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | RWE | 298 | Solar | signed | Rabbit's Foot Solar, Bowie County, Texas | [2026-06-11](https://www.powermag.com/meta-announces-ppa-with-rwe-for-298-mw-texas-solar-power-project/) |
| 2026-05-06 | Riot Platforms ([RIOT](https://supercyclehq.com/stock/riot-platforms.md)) | Terrestrial Energy ([IMSR](https://supercyclehq.com/stock/terrestrial-energy.md)) | 4000 | SMR | letter-of-intent | IMSR molten salt reactors co-located at Riot data center sites | [2026-05-08](https://www.datacenterdynamics.com/en/news/riot-platforms-inks-mou-with-terrestrial-energy-to-explore-smr-colocation-opportunities/) |
| 2026-04-13 | Oracle ([ORCL](https://supercyclehq.com/stock/oracle.md)) | Bloom Energy ([BE](https://supercyclehq.com/stock/bloom-energy.md)) | 2800 | Fuel cell | signed | Oracle Cloud Infrastructure on-site power expansion | [2026-04-13](https://www.reuters.com/business/energy/bloom-energy-supply-up-28-gw-fuel-cells-under-expanded-oracle-deal-2026-04-13/) |
| 2026-02-24 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Xcel Energy ([XEL](https://supercyclehq.com/stock/xcel-energy.md)) | 1900 | Mixed renewable | signed | Pine Island data center clean energy package, Minnesota | [2026-03-03](https://www.powermag.com/google-data-center-in-minnesota-would-be-powered-by-wind-energy-storage/) |
| 2026-01-09 | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Vistra Corp ([VST](https://supercyclehq.com/stock/vistra-energy.md)) | 2176 | Existing nuclear PPA | signed | Perry and Davis-Besse (Ohio) and Beaver Valley (Pennsylvania) | [2026-01-09](https://about.fb.com/news/2026/01/meta-nuclear-energy-projects-power-american-ai-leadership/) |
| 2026-01-09 | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | TerraPower | 2800 | SMR | signed | Natrium sodium fast reactor fleet, up to eight units | [2026-01-09](https://about.fb.com/news/2026/01/meta-nuclear-energy-projects-power-american-ai-leadership/) |
| 2026-01-09 | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Oklo ([OKLO](https://supercyclehq.com/stock/oklo.md)) | 1200 | SMR | signed | Aurora powerhouse campus, Pike County, Ohio | [2026-01-09](https://about.fb.com/news/2026/01/meta-nuclear-energy-projects-power-american-ai-leadership/) |
| 2025-12-08 | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | NextEra Energy Resources ([NEE](https://supercyclehq.com/stock/nextera-energy.md)) | 2500 | Solar + Storage | signed | US renewable and storage portfolio | [2025-12-10](https://www.energy-storage.news/nextera-signs-2-5gw-of-renewable-energy-agreements-with-meta-for-projects-across-us/) |
| 2025-12-08 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | NextEra Energy ([NEE](https://supercyclehq.com/stock/nextera-energy.md)) | n/a | Mixed renewable | signed | Strategic energy and technology partnership | [2025-12-08](https://www.nexteraenergy.com/company/news/nextera-energy-and-google-cloud-announce-landmark-strategic-energy-and-technology-partnership.html) |
| 2025-10-27 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | NextEra Energy ([NEE](https://supercyclehq.com/stock/nextera-energy.md)) | 615 | Nuclear restart | signed | Duane Arnold Energy Center, Palo, Iowa | [2026-04-15](https://www.ans.org/news/article-7942/nrc-shares-duane-arnold-restart-progress-at-public-hearing/) |
| 2025-08-21 | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Entergy Louisiana ([ETR](https://supercyclehq.com/stock/entergy.md)) | 2262 | Natural gas | signed | Hyperion data center generation, Richland Parish, Louisiana | [2025-08-21](https://www.datacenterdynamics.com/en/news/entergy-obtains-approval-to-construct-three-gas-facilities-to-serve-metas-2gw-data-center-in-louisiana/) |
| 2025-08-18 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Kairos Power / Tennessee Valley Authority | 50 | SMR | signed | Hermes 2, Oak Ridge, Tennessee | [2025-08-18](https://blog.google/company-news/outreach-and-initiatives/sustainability/google-first-advanced-nuclear-reactor-project-with-kairos-power-and-tennessee-valley-authority/) |
| 2025-07-15 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Brookfield Renewable Partners ([BEP](https://supercyclehq.com/stock/brookfield-renewable-partners.md)) | 3000 | Hydro | signed | Hydro Framework Agreement, PJM region | [2025-07-15](https://www.reuters.com/sustainability/climate-energy/google-inks-3-billion-us-hydropower-deal-largest-clean-energy-agreement-its-kind-2025-07-15/) |
| 2025-06-30 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Commonwealth Fusion Systems | 200 | Fusion | signed | ARC fusion plant, Chesterfield County, Virginia | [2025-06-30](https://blog.google/company-news/outreach-and-initiatives/sustainability/our-latest-bet-on-a-fusion-powered-future/) |
| 2025-06-26 | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Invenergy | 791 | Mixed renewable | signed | Four-project solar and wind portfolio | [2025-06-26](https://www.reuters.com/sustainability/climate-energy/meta-signs-deals-source-more-solar-wind-power-data-centers-2025-06-26/) |
| 2025-06-11 | Amazon Web Services ([AMZN](https://supercyclehq.com/stock/amazon.md)) | Talen Energy ([TLN](https://supercyclehq.com/stock/talen-energy.md)) | 1920 | Existing nuclear PPA | signed | Susquehanna Steam Electric Station, Pennsylvania | [2025-06-11](https://ir.talenenergy.com/news-releases/news-release-details/talen-energy-expands-nuclear-energy-relationship-amazon) |
| 2025-06-03 | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | Constellation Energy ([CEG](https://supercyclehq.com/stock/constellation-energy.md)) | 1121 | Existing nuclear PPA | signed | Clinton Clean Energy Center, Illinois | [2025-06-03](https://about.fb.com/news/2025/06/meta-constellation-partner-clean-energy-project/) |
| 2025-05-21 | Meta Platforms ([META](https://supercyclehq.com/stock/meta-platforms.md)) | AES Corporation | 650 | Solar | signed | Texas and Kansas solar portfolio | [2025-05-21](https://www.prnewswire.com/news-releases/aes-and-meta-sign-long-term-ppas-to-deliver-650-mw-of-solar-capacity-in-texas-and-kansas-302461791.html) |
| 2025-05-07 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Elementl Power | 1800 | SMR | signed | Three undisclosed US advanced nuclear sites | [2025-05-07](https://blog.google/feed/google-and-elementl-nuclear-energy-site-development/) |
| 2025-04-28 | xAI | Solaris Energy Infrastructure ([SEI](https://supercyclehq.com/stock/solaris-energy-infrastructure.md)) | 900 | Natural gas | signed | Stateline Power joint venture, Southaven, MS | [2026-08-05](https://www.sec.gov/Archives/edgar/data/0001697500/000162828026054349/sei-20260630.htm) |
| 2025-02-10 | CloudBurst Data Centers | Energy Transfer ([ET](https://supercyclehq.com/stock/energy-transfer.md)) | 1200 | Natural gas | signed | Central Texas AI data center gas supply | [2025-02-10](https://www.reuters.com/business/energy/energy-transfer-signs-natural-gas-supply-agreement-with-cloudburst-2025-02-10/) |
| 2025-01-07 | Endeavour Energy / Edged Data Centers | Deep Fission | 2000 | SMR | letter-of-intent | Borehole microreactors for the Edged data center platform | [2025-01-08](https://www.world-nuclear-news.org/articles/deep-fission-and-endeavour-announce-strategic-partnership) |
| 2024-12-18 | Switch | Oklo ([OKLO](https://supercyclehq.com/stock/oklo.md)) | 12000 | SMR | letter-of-intent | Oklo Aurora powerhouse fleet for Switch data centers | [2024-12-18](https://www.world-nuclear-news.org/articles/oklo-signs-power-agreement-with-data-centre-developer) |
| 2024-12-10 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Intersect Power | n/a | Solar + Storage | signed | Co-located data center and clean energy parks | [2024-12-11](https://www.utilitydive.com/news/google-intersect-power-tpg-rise-climate-data-center-renewables/735305/) |
| 2024-11-14 | American Electric Power ([AEP](https://supercyclehq.com/stock/american-electric-power.md)) | Bloom Energy ([BE](https://supercyclehq.com/stock/bloom-energy.md)) | 1000 | Fuel cell | signed | Gigawatt fuel cell procurement agreement | [2024-11-15](https://www.datacenterdynamics.com/en/news/bloom-energy-secures-1gw-fuel-cell-supply-deal-with-aep/) |
| 2024-10-16 | Amazon Web Services ([AMZN](https://supercyclehq.com/stock/amazon.md)) | X-energy / Energy Northwest ([XE](https://supercyclehq.com/stock/x-energy.md)) | 960 | SMR | signed | Cascade project, Richland, Washington | [2025-10-16](https://www.aboutamazon.com/news/sustainability/amazon-nuclear-small-modular-reactor-net-carbon-zero) |
| 2024-10-16 | Amazon Web Services ([AMZN](https://supercyclehq.com/stock/amazon.md)) | Dominion Energy ([D](https://supercyclehq.com/stock/dominion-energy.md)) | 300 | SMR | letter-of-intent | North Anna nuclear station site, Louisa County, Virginia | [2024-10-16](https://www.aboutamazon.com/news/sustainability/amazon-nuclear-small-modular-reactor-net-carbon-zero) |
| 2024-10-14 | Google ([GOOGL](https://supercyclehq.com/stock/alphabet.md)) | Kairos Power | 500 | SMR | signed | Kairos Power fluoride salt-cooled reactor fleet, Tennessee and other sites | [2024-10-14](https://blog.google/company-news/outreach-and-initiatives/sustainability/google-kairos-power-nuclear-energy-agreement/) |
| 2024-09-20 | Microsoft ([MSFT](https://supercyclehq.com/stock/microsoft.md)) | Constellation Energy ([CEG](https://supercyclehq.com/stock/constellation-energy.md)) | 835 | Nuclear restart | signed | Crane Clean Energy Center (Three Mile Island Unit 1), Pennsylvania | [2026-09-25](https://www.federalregister.gov/documents/2026/09/25/2026-19603/constellation-energy-generation-llc-christopher-m-crane-clean-energy-center-environmental-assessment) |
| 2024-05-23 | Wyoming Hyperscale | Oklo ([OKLO](https://supercyclehq.com/stock/oklo.md)) | 100 | SMR | signed | Aurora powerhouse for Wyoming Hyperscale campus, Evanston, Wyoming | [2024-05-23](https://oklo.com/newsroom/news-details/2024/Oklo-Partners-with-Wyoming-Hyperscale-to-Deliver-100-Megawatts-to-its-Data-Centers/default.aspx) |
| 2024-05-01 | Microsoft ([MSFT](https://supercyclehq.com/stock/microsoft.md)) | Brookfield Renewable Partners ([BEP](https://supercyclehq.com/stock/brookfield-renewable-partners.md)) | 10500 | Mixed renewable | signed | Global renewable energy framework agreement | [2024-05-01](https://www.cnbc.com/2024/05/01/microsoft-brookfield-renewable-energy-deal.html) |
| 2024-04-08 | Diamondback Energy (FANG) | Oklo ([OKLO](https://supercyclehq.com/stock/oklo.md)) | 50 | SMR | letter-of-intent | Aurora powerhouses for Permian Basin oil and gas operations | [2024-04-08](https://oklo.com/newsroom/news-details/2024/Oklo-Signs-LOI-to-Supply-50-Megawatts-of-Power-to-Diamondback-Energy/default.aspx) |
| 2024-04-02 | Equinix ([EQIX](https://supercyclehq.com/stock/equinix.md)) | Oklo ([OKLO](https://supercyclehq.com/stock/oklo.md)) | 500 | SMR | letter-of-intent | Oklo Aurora powerhouses for US Equinix data centers | [2024-04-05](https://www.datacenterdynamics.com/en/news/equinix-signs-deal-to-procure-up-to-500mw-of-nuclear-power-from-oklo-reactors-makes-25m-pre-payment/) |
| 2023-10-05 | Standard Power | NuScale Power / ENTRA1 Energy ([SMR](https://supercyclehq.com/stock/nuscale-power.md)) | 1848 | SMR | letter-of-intent | Two data center sites in Ohio and Pennsylvania | [2023-10-06](https://www.powermag.com/nuscale-gets-a-win-with-smrs-for-data-centers-in-ohio-and-pennsylvania/) |
| 2023-05-10 | Microsoft ([MSFT](https://supercyclehq.com/stock/microsoft.md)) | Helion Energy | 50 | Fusion | signed | Helion's first commercial fusion plant, Malaga, Washington | [2023-08-28](https://www.helionenergy.com/blog/announcing-helion-fusion-ppa-with-microsoft-constellation/) |

---

Source: https://supercyclehq.com/buildout. Data as of 2026-11-01. Prices are end-of-day closes, never live.